BS27-1: Putting a price on port repairs
News originally published by
DVIDS - GeorgiaNAHA MILITARY PORT, Japan – U.S. Air Force Airmen assigned to the 18th Comptroller Squadron, 18th Contracting Squadron and 718th Civil Engineer Squadron worked together to assess repair costs, negotiate contracts and process payments following simulated damage to Naha Military Port during Exercise Beverly Sword 27-1, Oct. 30, 2026.
The scenario simulated an attack that damaged port infrastructure, including bollards and rubber fenders used to secure vessels and prevent them from striking the dock. The exercise tested how finance, contracting and civil engineering personnel coordinated with simulated contractors to assess damage, determine repair requirements, prioritize resources and support the restoration of port operations.
Civil engineers from the 718th CES provided technical expertise on the damage and estimated repair timelines, while contracting personnel from 18th CONS coordinated with simulated contractors to establish repair costs and negotiate prices. Finance personnel from 18th CPTS verified documentation, ensured transactions met applicable requirements and processed payments to support the proposed repairs.
“Without funding, the mission can’t continue,” said U.S. Air Force Senior Airman Brittany Walsch, 18th CPTS financial operations technician. “Contractors need to be paid, and finance ensures the necessary payments are processed so repairs can move forward.”
Walsch served as a paying agent during the scenario, working with contracting personnel to determine the funding needed for repairs, verify documentation and process payments. The team used $25,000 USD in Japanese yen to simulate financial transactions, testing its ability to manage funding and execute payments in an operational environment.
With multiple damaged components affecting port operations, the team had to consider how each repair influenced the next step in restoring the port’s functionality.
“Our main priority was getting the boats back into the port,” said U.S. Air Force Senior Airman Neil Calica, 18th CONS contracting specialist. “Once that was addressed, we could focus on removing the materials, because each step depended on the one before it.”
The exercise demonstrated how financial readiness, contract execution and engineering expertise work together to restore critical infrastructure after an attack. By practicing these processes under simulated contingency conditions, the 18th Wing strengthened its ability to direct resources where they are needed most and sustain operations across the Pacific.
Legal Disclaimer:
EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.